Completion of installation of translucent str...
Completion of work on the installation of translucent window structures
10.11.2025 13:30
Completion of roof waterproofing works
Completion of work on the installation of the waterproofing coating of the roof
03.11.2025 14:30
Installation of floor screeds in common areas
Carrying out work on the installation of floor screeds in public areas
27.10.2025 13:00
Preparation for waterproofing terraces
Completion of the installation of the terrace screed and the start of work on the final waterproofing of the roof
20.10.2025 15:00
50% of the window structures are installed
Continuation of installation of translucent window structures
06.10.2025 13:00
Wiring of communications
Installation of sewer pipes and ducts of low-current networks
29.09.2025 14:30
Carrying out work on waterproofing the roof
The beginning of work on waterproofing the roof and the continuation of work on the installation of translucent window structures
22.09.2025 13:00
Completion of the roof screed installation
Completion of the installation of the roof screed and the start of work on the glazing of apartments
15.09.2025 14:00